To ask Her Majesty’s Government what are the terms of the review of HS2 being undertaken by Sir Jeremy Heywood; and when that review is expected to conclude.
A
Answered on: 11 May 2016

As is normal for large projects, the Cabinet Office’s Infrastructure and Projects Authority (IPA) is conducting assurance of the HS2 programme as it proceeds into its delivery phase. It is standard practice for this to include a small cross Government team, and not unusual for the Cabinet Secretary to take an interest on projects of this scale. ‎

The IPAs role on the Government's Major Projects Portfolio is to provide expertise in infrastructure and the financing, delivery and assurance of major projects, to support more effective management and delivery across government. The assurance exercise is expected to feed into the next steps on delivery.